How operate a Ship-lift?
                     ANIMATION OF THE                                  In the following, we will try to explain briefly the steps
                                                                       that take place during the lifting and launching operation
                   SHIPLIFT OPERATIONS                                 of mega yachts.

                                                                       In order to lift up a mega vessel, the first phase is to
                                                                       submerge the platform up to the sea bed draft height
                                                                       and after the vessel can move to moor inside the dock.
                                                                       Mooring can be assisted by cabstains winches installed
                                                                       along the dock walls.
                                                                       Afterward vessel mooring, platform rises until the keel
                                                                       blocks and engages the ship.
                                                                       Now the vessel is secured and can be lifted up to quay
                                                                       elevation by winches and transported on the yard by
                                                                       land carrier system.
                                                                       After the steel platform is secured by blocks; the land
                                                                       carrier can drive in platform below the mega yacht and
                                                                       engages the trestles by hydraulic jacks.
                                                                       With this  condition  accomplished, the  land carrier
                                                                       transports the vessel to the destination yard’s slot.
                                                                       Launching procedure is as above reversal.


                                                                       Conclusions
                                                                       “You should know that, the realization of the ShipLift
                                                                       project was a big satisfaction for our company” – starts
                                                                       Franco Pedron, Sales Director of Scandiuzzi – “we
                                                                       started our history in 1978 as small steelwork
                                                                       manufacturer and then the years pass and Scandiuzzi’s
                                                                       company grows. We acquired several experience in
                                                                       the steel construction from power to oil & gas sector,
                                                                       and later, also the naval sector became a knowledge.”
                                                                       Scandiuzzi has crossed many challenges, but we think
                                                                       that the philosophy that has always distinguished us is
                                                                       that we have been able to meet the challenges of the
          Above Two example of the screen’s software controlling the ShipLift   future. The ShipLift was a challenge overcame and we
          operations                                                   are ready to start a new.