Page 87 - 95
P. 87

sion financing is therefore similar to limited-or non-
            resource project finance, except that the revenues
            are received under the terms of a concession agre-
            ement.  The project will be approached in a similar
            way to limited-resource project financing in which
            the risks are isolated and allocated to those most
            qualified to bear them. 
            Each structure created is unique to the project, but
            generally BOOT/PPP is essentially a concession or
            global-service  contract  offered  by  a government
            and financed and undertaken by the private sector.
            A BOOT project often requires a promoter to enter
            into a number of contracts with a variety of parties.
            It is possible, however, for any particular project to
            have all, some or none of these contracts.  A typical
            simple structure created between the various par-
            ties is outlined in Figure 1.  A more complex struc-
            ture is necessary where the mending is sourced
            offshore in the international markets and is set out
            in Figure 2. 
                                                      Figure 1 - Example of a simple BOOT/PPP Structure
            The allocation of risks between the typical parties
            to a BOOT structure, as shown in the diagram, is
            regulated by the various agreements which the
            parties enter into. 

            •   The concession  company promotes the
                project and has the ultimate liability to the go-
                vernment under the concession agreement. 

            •   The concession agreement (sometimes
                referred to as the implementation or project
                agreement) is the primary contract between
                the government and the concession company
                and forms the contractual basis from which
                the other contracts are developed.  It entitles
                the concession company to build, finance and
                operate the facility and imposes conditions
                as to design, construction, operation, of the
                project and establishes the concession or
                operation period. 
            •   The equity investors’ and lenders’ secu-
                rity for their loans and investment is limited to
                the revenues to be received by the concession
                company.  They will therefore have considera-
                ble interest in the revenue forecasts produced   Figure 2 - Example of an international BOOT/PPP Structure
                by the concession company.  Likewise the
                two areas that place the concession company   offer some protection against time-and-cost
                and equity investors and lenders at risk are the   overruns. 
                construction contract and the operating con-
                tract.                                •   The operating contract: The lenders have to
                                                         be assured that an experienced operator will
            •   The construction contract: The parties   be available on completion of construction.
                would prefer a contractor to give a fixed
                price for completion by a fixed date without   •   The offtake contract.  This is one of the
                exclusions.  This is rarely possible in projects   key contracts.  As limited-resource projects
                of this nature.  Finance providers are therefore   are, by definition, funded on the security of
                only prepared to commit themselves to a   the future cash flow, there has to be some
                fixed  amount  because  if  the  project  costs   form of buyer.  Projects fall into two catego-
                more their funds will be in jeopardy due to   ries: those where the identity of the buyer
                the interest burden.  Lenders will not accept   is obvious, for example toll roads and some
                the risk of delay to completion, although they   power stations and those where there is
                will normally provide a standby facility to   physical product which has to be sold, of-



                                                                                     Impiantistica Italiana - Marzo-Aprile 2022  81 81
   82   83   84   85   86   87   88   89   90   91   92