Page 48 - Impiantistica industriale
P. 48

ENGINEERING





                                Despite the onset challenges,         round 2020 Project’.
                                our Wood and Sarlux teams             Final project Level 3 baseline schedule included at
                           “adapted quickly and remained              about 30,000+ activities.
                                                                      Wood’s project schedule and material availability
                                focused on the successful and         integrated system (AMUSE Construction®) pre-
                                safe delivery of this milestone       sented added value in the itemised and bulk ma-
                                project. New working methods          terial prefabrication and installation forecast asses-
                                                                      sments.
                                never tested before became new        The project baseline and AMUSE Construction®
                                day-by-day procedures                 were essential tools during the pre-turnaround
                                                                      and turnaround periodic reviews to detect poten-
                                                                      tial deviation from planned activities assessing the
                                                                      forecast time impacts and consequent mitigation
                            the outcomes regarding 3D simulations and heavy   revisiting activities sequences.
                            lifting studies, describing step by step:  The approach to the project plan review involving
                            •   Temporary dismantling of the existing refine-  all refinery stakeholders, engineering companies,
                                ry infrastructures interfering during each lifting   critical vendors and construction contractors was
                                and/or translations operation;        agreed prior to the turnaround kick-off.
                            •   Preparatory works as reinforced concrete   Methodology enabled the team to complete the
                                slab, wooden mats location, backfilling exten-  pre-turnaround on 4 March 2020 in line with the
                                sion for cranes and trailer load distribution;  baseline programme and with a clear overall status
                            •   Protecting required for existing refinery under-  of activities at the turnaround start.
                                ground pipes, cables, pits during the heavy lift
                                operation;
                            •   Temporary laydown positions of each element/ Turnaround control
                                equipment during the site fabrication;  and management
                            •   Path to be followed by each element/
                                equipment when moved from laydown posi-  Full visibility of activities progressed and achie-
                                tion toward the lifting position;     vements made were provided to the refinery and
                            •   Cranes lifting and trailer movement sequen-  project management. These reports allowed quick
                                ces.                                  decisive action to be made and were  one of the
                                                                      main factors in driving turnaround success.
                            Pre-turnaround                            Considering this fundamental aspect, Wood deve-
                                                                      loped specific turnaround progress measurement
                            and turnaround planning                   system and procedures.
                                                                      The huge amount of progress data to collect,
                            A  continuous  interactive  process  between  con-  analyse and manage, and the daily frequency of
                            structability studies and sequence planning im-  progress updates was a critical issue. Wood set
                            plemented since the front-end engineering design   up fully integrated electronic progress file exchan-
                            (FEED) phase enabled priorities and criticalities of   ge between Wood  and  construction  contractors
                            engineering, procurement and construction to be   reducing input, data time collection and potential
                            addressed. This approach provided a robust and   mistakes from manual input.
                            consistent overall baseline schedule that became   Following the receipt of progress data, Wood deve-
                            the reference for all parties involved in the ‘Turna-  loped the daily report including progress achieve-






















       Pre-turnaround and
       turnaround 2020 Project
       WBS

       46 46  Impiantistica Italiana - Novembre-Dicembre 2020
   43   44   45   46   47   48   49   50   51   52   53