ORF Onshore Receiving Facilities







            Contribution to the execution phase of the ‘First Oil’ for the first
            foreign Oil&Gas company to produce oil since the approval of
            Energy Reform in Mexico (2013),  as part of a new greenfield
            development project located in the Campeche Bay off the coast

            Pino Gozzo, Engineering Manager
            DG IMPIANTI INDUSTRIALI S.P.A.




































                       he overall project development consists   full field production (named PHASE 2) started in 2022
                       of an offshore platform, which delivers   by means of an FPSO, will increase production up to
                       the production to the Onshore   100,000 barrels of oil per day.
                       Receiving Facility (ORF) located in   DG Impianti scope included engineering, procurement,
                       Sanchez  Magallanes,  through  a   construction,  commissioning  and  start-up  of  ORF,
            T multiphase sealine. After separation at   including the tie ins with PEMEX areas in Bateria San
            ORF,  production  is  directed  to  Pemex’s  San  Ramón   Ramon and ECO San Ramon.
            plant for treatment.
            The project has been developed in a fast track
            approach. The production has started since two years  Phase 1 Project Detail
            and a half from the drilling of the first well in Area 1 and   The plant consists of a process area, which includes
            in less than one year since the approval of the   pig trap area and separation unit, (with two separators,
            development plan, totally fulfilling the expectations of   one slug catcher, seven measurement skids and the
            the Mexican Government, aimed to increase the overall   flaring system); utility area, (which includes the power
            production in the country.               generation, the compressed air system, the fuel gas
                                                     skid, the nitrogen unit); building area ( control and
               “This project has been developed      electrical room); telecommunication system  and
                    in a fast track approach         firefighting system.

                                                     The manifold unit, which include the manual choke
            This early production phase (named PHASE 1)   valve, the HIPPS and the pressure transmitters for
            produces up to 15,000 barrels of oil per day, while the   alarm and process shut down, receives the multiphase