For the considered operating conditions the refri-
            geration compressor will be of centrifugal type. For
            the base case, the external power grid has been
            considered capable to supply the required po-
            wer to drive the refrigerant compressor. Common
            motor driver and dedicated motor driver solutions
            have been considered, with different electrical sy-
            stem design and hence different substation buil-
            ding arrangement.

            An alternative solution based on an aero-derivative
            gas turbine is also available, considering the nitro-
            gen and the gas refrigerant compressors mounted
            on the same shaft.

            The heating system is ensured by a hot water cir-
            cuit that supplies heat mainly to the amine regene-
            ration reboiler and to the molecular sieve regenera-
            tion first heater (the trim heating of regeneration gas
            is performed by an electrical heater).    genic  bullets, the  estimated project duration   Small scale LNG plant 3D
            Instrument air and nitrogen are produced within the   is 23 months from effective date to Ready for   model
            LNG plant. Potable, service and demineralized wa-  Start-Up.
            ter is supplied from external sources, but could be   It is based on an existing typical FEED that needs
            produced on site, should the necessity arise.  little consolidation to cope with the actual project
                                                      requirements, i.e. small adjustments to cope with
            The  design  approach  based  on  the  proposed  li-  actual gas characteristics and site conditions.
            quefaction concept leads to a compact layout of   This  FEED  consolidation  period  is  estimated  at
            approximately 1,500 m .                   two months and is performed during project ne-
                              2
                                                      gotiation and before project effective date so that
            Two alternatives have been evaluated for storage:  purchase orders for Long Lead Items (LLIs) can be
            •   Vacuum insulated cryogenic bullets    done within the two initial months of the project.
            •   Atmospheric Full containment Tank     LLIs are the equipment having a delivery time
                                                      longer than 12 months and are typically:
            For the first storage option a limited LNG storage   - the compression train
            capacity is considered. The produced LNG from   - the boil off gas compression
            liquefaction unit is stored in 8 horizontal cryogenic   - the turbo expanders
            bullets (800 m  each) and then exported through   - the cold box
                        3
            LNG  trucks  or  LNG  barge.  The  selection  of  the   - the vacuum insulated cryogenic bullets
            cryogenic bullets simplifies the BOG management,
            but  it  is  applicable  to  smaller  overall  storage  ca-  The construction strategy is based on maximizing
            pacity.                                   the portion of the plant to be delivered in modules.
                                                      Equipment and systems having a shorter delivery
            For the second option, the produced LNG is sto-  time will hence be assembled in modules, and
            red in a 30,000 m  storage tank. The boil-off gas   they will typically include:
                           3
            produced in the tank is compressed, used for mo-  - pressure vessels (separators, scrubbers…)
            lecular sieve regeneration and then recycled to the   - air coolers
            pre-treatment. A part of the boil-off gas is used to   - pumps
            supply fuel users.                        - and associated bulk items (piping, structure,
            The stored LNG can be exported to LNG trucks or   cables)
            to small scale LNG carrier.               The fabrication  of the modules  will start after  8
                                                      months of the project effective date and will be
            Execution strategy                        performed in a high efficiency yard.
            The execution strategy is based on a standard and   LLIs  will be built at vendors  workshops and be
            pre-engineered gas treatment and liquefaction sy-  delivered directly at site, assembled in skids for
            stem. The presence of this standardized design   the rotating equipment and loose for the static
            package is essential as it leads to significant savin-  equipment (cold box and bullets).
            gs in terms of engineering documents preparation,   During modules and LLIs fabrication and manufac-
            purchasing activities and modules construction   turing, the site is prepared to be ready to accom-
            and installation.                         modate them (foundations, buildings, some piping
            For the option based on vacuum insulated cryo-  and structures) and some stick-built installation